Çamsan Ordu MDF 3 Factory Project is a project that increases capacity of Çamsan Ordu 2.5 times on the basis of turnover and the production capacity 2 times. The technological partnership of the modern facility, which includes CPS + Press Technology, has been made by German DIEFFENBACHER. The project duration is 6 months from the contract date.

Electrical Assembly Works and Çamsan Ordu MV Modernization Project

Armin Electric Construction Industry and Trading Inc. Co. undertook electrical, automation and instrumentation works, transformer supply and assembly, supply and assembly of MV Cells, supply and assembly of LV Panels within the scope of the project.

Within the scope of Çamsan Ordu MV Modernization Project, 32 new cells were supplied instead of the existing 38 cells. In addition to the dismantling of the existing cells, the supply, assembly and commissioning of the new cells were carried out by us as Armin Electric.