You are here:

H.669 Referenced 154 kV (~ 5.4 km) 1272 MCM and (~ 34.2 km) 2x1272 MCM Conductor Bahçe- Osmaniye 2 (Renovation) ETL Bid Unit Price Complete Installation Work

Within the scope of the work, the line route was determined by marking the pole center and directions and sub-assembly excavations started, and after the excavations, the sub-assembly was completed by assembling the Galvanized Stubs in accordance with the project. The installation of Top Mount Galvanized Iron Pole started by paying attention the concrete setting times. The Phase and OPGW Conductor Drawing of the lines whose top assembly was completed was made without any problem and the Energy Transmission Lines were commissioned smoothly after the acceptance by the TEİAŞ teams.