İTM.315 Referenced 154 kV Rize Substation Renewal (DOKAP) Construction Work

The main scope of the İTM.315 Referenced 154 kV Rize Substation Renewal (DOKAP) construction work is the complete renovation of the existing transformer center, provided that it is in continuous operation. First of all, the buildings that will be needed will be constructed, function of the system will be continued from the newly built buildings and system with a temporary transformer and feeder, and the old buildings and switchgear will be demolished and renewed. From the new buildings, new switchgear and transformers will be commissioned and temporary feeders and transformers will be unloaded. The current general progress is about 35% and the work is ongoing. The work is planned to be completed in July 2021.