154/33 kV Pekmezli Substation Extension Project

The 154/33 kV Pekmezli TM Extension Project (GAP) was carried out byus in collaboration with TEİAŞ 12th Regional Directorate.

CONSTRUCTION WORKS

The construction of a 2-story Metal Clad Building, which includes a basement for cable galleries, rooms for internal transformers, and metal clad cells, has been completed. The construction of the equipment and pylon foundations for the newly installed transformer feeder and the cable channels has been completed; the steel installation and the renewal of the cable channels, transformer foundations, and site gravel in the existing energized
switchyard in accordance with TEİAŞ Approved Projects has been completed. The renovation work on the existing control building has been completed.

ELECTRICAL WORKS

In accordance with the General Technical and Installation Specifications and the projects approved by TEİAŞ, the following were supplied and installed: 154/33 kV 100 MVA Power Transformer, 2 Auxiliary Service Transformers (250 kVA, Dry Type), 154 kV Shunt Capacitor Bank, Control and Relay Panels, and Field Distribution Boxes have been supplied and installed, and the installation of MV XLPE Cable in accordance with the EKAT MV Cable Laying Specifications, Primary Installation, and Secondary Cabling works have been completed.